Client: CTA Architects

Owner: New York City School Construction Authority (NYCSCA)

Project Value: $2,800,000

Contract Duration: 2014

Services Provided: Cost Management, Cost Estimating

NYCSCA  Universal Pre-K Center Fit-Out at Bishop Kearney High School

Brooklyn, NY

This project involved providing cost estimating services for the renovations of the 10,545 SF kindergarten classroom wing at Bishop Kearney High School in Brooklyn, NY. The project scope included demolition of interior classrooms, offices, and bathrooms on the 1st, 2nd, and 3rd floor and exterior site work. New construction included partitions, floor, ceiling and wall finishes, windows, doors, bathroom specialties,  classroom and office furnishings. The scope of work included various structural and MEP services including building system controls, plumbing fixtures and piping, light fixtures, receptacles, tel/data systems, fire alarm system, public address system, and video surveillance.