Hospital of Central Connecticut Data Relocation Night.jpg

Client: Bostwick Architects, LLC.

Owner: The Hospital of Central Connecticut

Project Value: $5,000,000

Contract Duration: 2009

Services Provided: Cost Management, Cost Estimating

 

Hospital of Central Connecticut - Data Center

Newington, CT

This project involved providing design-development cost estimates for the proposed relocation of the data center in the Hospital of Central Connecticut. The work entailed a retrofit of existing space on the ground floor above the basement to accommodate the new data center. The state-of-the-art data center occupies space formerly part of the hospital’s laundry area.  The converted space is secured from within the hospital and the sophisticated data systems provided with redundant backup technology.