Client: Ricci Green

Architect: Tevebaugh Associates

Owner: State of Delaware

Project Value: $4,000,000

Contract Duration: 2016

Services Provided: Cost Estimating, Cost Management

 

Delaware Courts – Justice of Peace Court Fit Out

Wilmington, DE

This project involved providing cost estimating services to Ricci Greene at the conceptual phase of this project.

The project consists of the interior fit out of a new court building for the State of Delaware. The project included 14,000sf of courts and associated space, including four courtrooms, associated holding cells, chambers, and ante space, as well as library, file, and support space for employees.

Multiple layout options were investigated, as well as studies on phased construction.