Central New York Psychiatric Center.jpg

Client: RTKL Architecture and Engineering

Owner: Central New York Psychiatric Center (CNYPC)

Project Value: $9,000,000

Contract Duration: 2012

Services Provided:  Cost Management, Cost Estimating

Central New York Psychiatric Center - Generator Replacement 

Utica, NY

This project involves providing cost estimating services at all stages of the project design for the existing emergency generator replacement at the Utica Psychiatric Center. The scope of services for this project include demolition of the existing 300 KW generator, associated feeders, day tanksand oil tank; installation of the new 1,500 KWA generator with weatherproof enclosure, new feeders, temporary 300 KWA generator during construction period, new 10,000 gallon diesel tank, 325 gallon day tank with associated piping and new switchgear. The project required shutdowns. The estimate covered work performed during premium time.