Bangor Court.jpg

Client/Architect: WSP Flack + Kurtz

Owner: Department of Citywide Administrative Services (DCAS)

Project Value: $3.5 Million

Contract Duration: 2012

Services Provided: Cost Management, Cost Estimating

 

 

Brooklyn Supreme Court Renovation/Boiler Replacement

Brooklyn, NY

The project involves boiler plant upgrade at the existing courthouse building, isolating from the adjoining building and creating independent boiler plant. The scope of work includes removal of two 1,000 BHP and provide two new 125PSI 300 BHP; provide controls, ventilation, new control systems, economizers on bolier stocks, field-fabricated boilers, ne wheat pump systems. Cost estimating services are provided from the conceptual level of design thru all stages of the design development.